Effectiveness of Competitive Prototyping and Preliminary Design Review Prior to Milestone B
Loading...
Authors
Fast, William
Subjects
Advisors
Date of Issue
2014-04-01
Date
Publisher
Monterey, California. Naval Postgraduate School
Language
Abstract
The 2013 Annual Report on the Performance of the Defense Acquisition System (USD[AT&L], June 28, 2013) identified a need for additional analysis of recent acquisition policies (DoDI 5000.02, December 2008) to reduce program technical risk by requiring competitive prototyping for risk reduction and a Preliminary Design Review (PDR) before Milestone B. This research uses cost and schedule estimates from Major Defense Acquisition Programs (MDAPs) to determine if competitive prototyping and PDRs held prior to Milestone B have resulted in mature technologies (defined as Technology Readiness Level 6 or above) and subsequently reduced program cost and schedule slippage.
Type
Report
Description
Series/Report No
Department
Organization
Identifiers
NPS Report Number
NPS-AM-14-C11P20R02-071
Sponsors
Naval Postgraduate School Acquisition Research Program
Funding
Format
Citation
Distribution Statement
Rights
This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.