Requisition throughout time simulation at Naval Supply Center San Diego

Loading...
Thumbnail Image
Authors
Lynch, Michael G.
Ulrich, Charles Howard
Subjects
Simulation
Throughput time
Naval Supply Center, San Diego
Processing time
Stock point simulator
Advisors
Richards, F. Russell
Date of Issue
1973-03
Date
March 1973
Publisher
Monterey, California. Naval Postgraduate School
Language
en_US
Abstract
A computer model which simulates the processing of requisitions for standard stock material at NSC San Diego is constructed. The model is designed to enable NSC San Diego to determine those work stations which are bottlenecks and to view the effects of changes in total throughput time caused by changes in manpower resources and administrative procedures. Output from the computer simulation model includes an analysis of throughput time by issue priority group, and summary data on work center utilizations and delay times. Total throughput time is compared to Uniform Material Movement and Issue Priority System time standards. The automated materials handling system seems to achieve its goals; however large delays are seen to occur in the staging area where items await local transportation. These delays are reflected most critically in the statistics for the percentage of issue priority group two material shipped on time. Variations of the basic model were analyzed. The combination of a six day workweek and an increased local delivery schedule resulted in substantial improvement.
Type
Thesis
Description
Series/Report No
Department
Operations Analysis
Organization
Naval Postgraduate School (U.S.)
Identifiers
NPS Report Number
Sponsors
Funder
Format
Citation
Distribution Statement
Approved for public release; distribution is unlimited.