Enhancing the enhanced scenario-based method of cost risk analysis

Download
Author
Hooper, Seth T.
Date
2011-12Advisor
Nussbaum, Daniel
Gates, William
Metadata
Show full item recordAbstract
The current S-Curve method of cost risk analysis for major DON acquisitions projects does not accurately estimate actual cost when the program reaches Full Rate Production. Another, sometimes more effective method of measuring cost risk, is by using the enhanced scenario-based method (eSBM) of risk analysis. The reason that cost estimations from the milestone B costs are inaccurate is that very little, if any, real information about the project is known. eSBM allows managers a less statistically tasking method of determining cost risk for a project while still maintaining the requirements of the Weapons System Acquisitions Reform Act. The key factors in measuring the usefulness of eSBM should be focused on the acquisition strategy being used for the project and the time frame from Milestone B to later Milestones. I presume that different acquisition strategies will yield different levels of success in estimating cost risk for eSBM.
Rights
This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.Collections
Related items
Showing items related by title, author, creator and subject.
-
Advanced Earned Value Management: Extending Program Management Theory Through Value Centric Turbulence Flow Methods
Jones, Raymond (Monterey, California. Naval Postgraduate School, 2021-05-20); SYM-AM-21-140Current methods of measuring acquisition project performance are based upon generations of old cost models that compare budgets with expenditures. These methods provide little in the way of forecasting, leaving the project ... -
Advanced Earned Value Management: A Proposal for Extending Program Management Theory Through Value Centric Turbulence Flow Methods
Jones, Raymond (Monterey, California. Naval Postgraduate School, 2021-05-10); SYM-AM-21-050Current methods of measuring acquisition project performance are based upon generations of old cost models that compare budgets with expenditures. These methods provide little in the way of forecasting, leaving the project ... -
Monitoring Risk Response Actions for Effective Project Risk Management
Kujawski, Edouard; Angelis, Diana (Wiley Periodicals, Inc., 2010);Complex projects typically involve high-consequence, project-specific risks that require detailed analysis and for which risk response actions (RRAs) need to be developed and implemented. The risk picture is dynamic. The ...