Dynamic Cost-contingency Management: A Method for Reducing Project Costs While Increasing the Probability of Success
Abstract
In the real world, Money Allocated is Money Spent (MAIMS). As a consequence, cost underruns are rarely available to protect against cost overruns, while task overruns are passed on to the total project cost. The combination of the probabilistic aspects of project costs and the MAIMS principle have important implications for budget allocation and the management of contingencies. Project costs depend not only on the desired probability of success but also on budget allocation and contingency management. This is in contrast with both deterministic practices that allocate a percentage of the project baseline cost for contingency as well as today de-facto probabilistic cost analyses that provide a cost contingency independent of the budget-allocation strategy. The realistic modeling of cost uncertainties and the MAIMS principle provide a framework for developing a viable cost-management strategy for allocating baseline budgets and contingencies. Based on this analysis, the project manager can maintain a realistic project-wide contingency and dynamically distribute it to the individual risks on an as-needed basis. Projects that implement dynamic cost-contingency management based on these principles are likely to achieve a higher probability of success and cost less.
Description
Proceedings Paper (for Acquisition Research Program)
NPS Report Number
NPS-AM-07-035Related items
Showing items related by title, author, creator and subject.
-
On-line real-time management information systems and their impact upon user personnel and organizational structure in aviation maintenance activities
Bayma, Benjamin A. (Monterey, California. Naval Postgraduate School, 1979-12);The introduction of a new technology into an organization can significantly impact the organization's effectiveness. Some possible effects on user personnel and organizational structure during and after the implementation ... -
ANALYSIS OF PRICE AND PROGRAM GROWTH IN OPERATION AND MAINTENANCE, NAVY
Cromie, Christopher T.; Long, Colton J.; Weeks, Damen C. (Monterey, CA; Naval Postgraduate School, 2020-06);For decades, operation and maintenance (O&M) has been growing as a share of the defense budget. To understand the drivers of that growth, we examined OP-32 and OP-32A data, which are the summary of price and program changes ... -
An analysis of current Operational Contract Support planning doctrine
Kimsey, Sara D. (Monterey, California: Naval Postgraduate School, 2015-09);The purpose of this project is to analyze Operational Contract Support (OCS) planning doctrine for maturity and applicability to single services. In the OCS Initial Capabilities Document, the Department of Defense declared ...