Estimating Total Program Cost of a Long-Term, High-Technology, High-Risk Project with Task Durations and Costs That May Increase Over Time
Loading...
Authors
Brown, Gerald G.
Grose, Roger T,
Koyak, Robert A.
Subjects
Advisors
Date of Issue
2006
Date
2006
Publisher
Language
Abstract
We plan a long-term project schedule for which the total budget depends upon the year the project finishes. Each task in the project can begin only when all its predecessor tasks have been completed, and each task has a range of feasible durations with a month-by-month cost profile for each duration. A task start can be delayed, but once started for some chosen duration, a task cannot be interrupted. Each task suffers some risk of delay and changed cost. Ignoring budget constraints, we use Monte Carlo simulation of the duration of each task in the project to infer the probability distribution of the project completion time. We then optimize a deterministic project schedule following budget guidance. Finally, we successively reschedule as the project progresses, simulating annual review of the active tasks, and possibly delaying each active task's duration and changing its monthly costs for its forecast duration. We do not require an independence assumption, so we can accommodate learning effects from completed tasks. U.S. Army Future Combat Systems (FCS) is our motivating application. FCS is a complex of information technologies, sensors, and command systems expected to require more than a decade and $16 billion to develop. The U.S. General Accounting Office finds FCS at significant risk of cost and schedule growth, and suggests two alternatives to a baseline Army plan. We analyze these three alternate project plans for FCS to discover which one can most likely be completed soonest and cheapest.
Type
Article
Description
Military Operations Research, 11, 2006, pp. 41-62.
Series/Report No
Department
Operations Research (OR)
Organization
Identifiers
NPS Report Number
Sponsors
Funder
Format
Citation
Brown, G.G., Grose, R.T, and Koyak, R.A Total Program Cost of a Long-Term, High-Technology, High-Risk Project with Task Durations and Costs That May Increase Over Time. Military Operations Research, 11, 2006, pp. 41-62.
Distribution Statement
Rights
defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.